The moment an investment starts is the most common reason for losing public aid. A single signed contract or a single advance payment can mean that the entire investment no longer qualifies for support.
What “start of the investment” means
Under public aid rules (including Article 2(23) of Commission Regulation (EU) No 651/2014 – GBER), the start of the investment is whichever of the following happens first:
- the start of construction works, including earthworks,
- the first legally binding commitment to order equipment – e.g. a contract with a supplier, a confirmed order, payment of an advance or a deposit,
- any other commitment that makes the investment irreversible.
One such event is enough – even if it concerns only a single machine.
What you can do before the decision
The rules do not treat the purchase of land or preparatory work as the start of the investment. Before the decision you can therefore safely:
- buy land,
- obtain a building permit and an environmental decision,
- commission a feasibility study and designs,
- collect and negotiate offers that do not bind the company.
Bear in mind, however, that expenses incurred before the decision will not count as eligible costs.
The most common pitfalls
- an advance payment “to reserve a production slot” for a machine,
- a contract called “conditional” that cannot be withdrawn from without high penalties – in practice it is binding,
- “preparatory” construction works, e.g. excavations or foundations,
- an order placed by an affiliated company from the same group,
- starting purchases right after submitting the application, without waiting for the decision.
Letter of intent and conditional contract
A letter of intent or a contract that can be withdrawn from without significant cost is, as a rule, not a binding commitment. The safest approach is to state in the contract that it enters into force only after the support decision has been issued. What counts is the content of the document, not its title – so it is worth showing it to an adviser before signing.
EU grants
For grants, the moment a project may start is defined by the rules of the specific call – most often the project may start at the earliest on the day after the grant application is submitted. Starting work before the application is submitted always rules out a grant. If a company combines a grant with the Polish Investment Zone exemption, the stricter rule applies, i.e. the start only after the support decision has been issued.
What to do if the investment has already started
A support decision cannot be obtained for an investment that has already started. You can, however, plan a further, genuinely separate stage – e.g. a new production line or an extension of the hall – as a separate investment and obtain a decision for it before it starts. The separation must be real, not just formal, so it is worth analysing such a plan with an adviser.
A safe order of steps
- Consultation and a preliminary investment plan.
- Collecting offers and talking to suppliers – without binding commitments.
- Submitting the application for a support decision.
- Receiving the support decision.
- Only then: contracts, orders, advance payments and construction works.
This article is for information only and does not replace an individual analysis of your investment.